November 30, 2018 | Category: District A | Tagged as: Fleur de Lis
Command Construction Industries, LLC crews are nearly complete with the Fleur de Lis Drive Phase III Reconstruction Project between 30th Street and Old Hammond Highway in the West End neighborhood.
October 5, 2018 | Category: District A | Tagged as: Fleur de Lis
Command Construction Industries, LLC crews have now completed 80 percent of the Fleur de Lis Drive Phase III Reconstruction Project between 30th Street and Old Hammond Highway in the West End neighborhood.
September 21, 2018 | Category: District A | Tagged as: Fleur de Lis
Command Construction Industries, LLC crews have now completed 78 percent of the Fleur de Lis Drive Phase III Reconstruction Project between 30th Street and Old Hammond Highway in the West End neighborhood.
August 14, 2018 | Category: District A | Tagged as: Fleur de Lis
Command Construction Industries, LLC crews have now completed 76 percent of the Fleur de Lis Drive Phase III Reconstruction Project between 30th Street and Old Hammond Highway in the West End neighborhood.
July 17, 2018 | Category: District A | Tagged as: Fleur de Lis
Command Construction Industries, LLC crews have completed 72 percent of the Fleur de Lis Drive Phase III Reconstruction Project between 30th Street and Old Hammond Highway in the West End neighborhood.
The City of New Orleans and the Sewerage & Water Board are hiring.
Find jobs with the City
Find jobs with S&WB
Connect to First Source
You can contact us directly at roadwork@nola.gov or by phone at (504) 658-ROAD (7623).