The Lower Ninth Ward Northeast Group B project began in late June with the excavation of St. Maurice Avenue (between North Roman and North Prieur streets). Crews are currently excavating in preparation of installing new water and drain lines. Residents will be notified of work that will impact their access and/or cause disruption to their utilities.
This $5.8M project was designed by Neel-Schaffer, Inc. and will be constructed by Fleming Construction Co, LLC.
This is a full-depth reconstruction, but work varies block by block:
- Replace damaged underground water, sewer and drainage lines;
- Repave the roadway;
- Replace damaged sidewalks and driveway aprons; and
- Install Americans with Disabilities Act-compliant curb ramps at intersections.
Information about this project was made available at a pre-construction public meeting on May 05, 2020. The presentation can be found here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).