The $8.1M West Bank Group B project, which began construction in March 2020, has now resumed on Richland Road as well as Odeon and Magellan streets with asphalt pavement installation. Residents will be notified by flyers and “No Parking” signage when the project moves to their block.
Designed by Buchart Horn, Inc. the project is being constructed by Fleming Construction Company, LLC. Click here to view a map of the project. The scope of work varies by block and includes the following:
- Patch Mill/Overlay: Repaving the asphalt roadway from curb-to-curb and repair damaged sidewalks;
- Patch Concrete: Removing damaged portions of the concrete roadway and replace it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replace it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
The City of New Orleans held a public meeting about the project in March 2020 to discuss anticipated impacts to the community. View a copy of the meeting presentation here. For more information about this project and other upcoming work, please visit roadwork.nola.gov or call 504.658.ROAD (7623).