Boh Bros Construction Co., LLC crews completed drainage line placements and installations on Oriole Street in late December on the Lake Terrace and Oaks Group D infrastructure improvement project. Crews continue to work in close collaboration with the Sewerage and Water Board of New Orleans to install new waterlines within the project limits. Crews are also working on Oriole and Kildeer streets but have now shifted to accommodate COX Communications activity happening in this area. Residents will be notified ahead of any work that will involve utility disruptions and / or impacts to parking and access to their street.
Construction on this full-depth reconstruction project started in June 2020 and is expected to be complete in summer 2021, weather permitting. The scope of work for the $5.8M project may include:
- Replacing damaged underground water, sewer and drainage lines;
- Repaving the roadway;
- Replacing damaged sidewalks and driveway aprons; and
- Installing Americans with Disabilities Act (ADA)-compliant curb ramps at intersections.
Mott MacDonald is the project designer. A community conference call about the project was held on May 20, 2020. You can access the presentation here. For more information about this project and other upcoming work, please visit roadwork.nola.gov or call 504.658.ROAD (7623).