Contact Us: ose@nola.gov | (504) 658-7623
March 22, 2017 | Category: District A | Tagged as: Fleur de Lis
Construction on third phase of Fleur de Lis Dr. between 30th Street and Old Hammond Highway, is now under way.
March 13, 2017 | Category: District A | Tagged as: Lakeview
The Lakeview North Group A project consists of repairing damaged sidewalks, driveway aprons and curbs. This project is slated to begin April 2017 and will take approximately one year to complete.
March 7, 2017 | Category: District A
A full-depth reconstruction project began on South Johnson and Melodia Court in Nov. 2016. The $1.8 million project scheduled to be completed this summer.
The City of New Orleans and the Sewerage & Water Board are hiring.
Find jobs with the City
Find jobs with S&WB
Connect to First Source
You can contact us directly at ose@nola.gov or by phone at (504) 658-7623.