Latest News

ROADWAY PAVING TO BE COMPLETE BY DECEMBER ON READ EAST GROUP B PROJECT

November 19, 2020   |    Category: District E    |   Tagged as: Read Blvd

ROADWAY PAVING TO BE COMPLETE BY DECEMBER ON READ EAST GROUP B PROJECT

Beverly Construction Co., LLC, crews expect to wrap up roadway restoration work on the Read Boulevard East Group B project by December. Crews completed a substantial amount of the remaining water line work and sidewalk operations through the month of October and are now focused on roadway paving.

PAVING AND WATER LINE WORK CONTINUE ON READ EAST GROUP D

October 21, 2020   |    Category: District E    |   Tagged as: Read Blvd

PAVING AND WATER LINE WORK CONTINUE ON READ EAST GROUP D

Beverly Construction crews continue water line and paving operations on the Read Boulevard Group D project. Crews have less than 10 water line tie-ins remaining before the project can move into the substantial completion phase. New water lines, upgraded drainage, and roadway paving are still on track to be completed this fall.

CONCRETE POURS APPROACH COMPLETION ON READ EAST C PROJECT

October 21, 2020   |    Category: District E    |   Tagged as: Read Blvd

CONCRETE POURS APPROACH COMPLETION ON READ EAST C PROJECT

Palmisano Construction crews began pouring new sidewalks, driveway aprons and roadway on the Read East Boulevard Group C project in September. They expect to complete Maid Maron and Sherwood Drive in October. Crews continue to perform water line work that had to be rescheduled due to the threat of inclement weather. Paving operations will begin immediately following the water line work.

WATER LINE OPERATIONS AND PAVING OPERATIONS 80 PERCENT COMPLETE ON READ EAST GROUP B PROJECT

October 21, 2020   |    Category: District E    |   Tagged as: Read Blvd

WATER LINE OPERATIONS AND PAVING OPERATIONS 80 PERCENT COMPLETE ON READ EAST GROUP B PROJECT

Beverly Construction crews have completed 80 percent of the water line and roadway restoration work on the Read Boulevard East Group B project. Tie-ins were successfully completed throughout the project through September. Crews have also completed roadway restoration in many areas, including Sierra Madre Drive. Crews will continue work on the remaining water line work and sidewalk operations through the month of October.

WATER LINE OPERATIONS CONTINUE ON READ EAST GROUP B PROJECT

September 30, 2020   |    Category: District E    |   Tagged as: Read Blvd

WATER LINE OPERATIONS CONTINUE ON READ EAST GROUP B PROJECT

Beverly Construction, LLC. will continued water line tie-ins as part of the  Read Boulevard East Group B project in September. Tie-ins were successfully completed throughout the project in August. Crews have also completed roadway restoration in many areas, including Sierra Madre Drive. Upon completion of the water line tie-ins, this project will  be at 80 percent completion.

Displaying results 16-20 (of 87)
 |<  <  1 - 2 - 3 - 4 - 5 - 6 - 7 - 8 - 9 - 10  >  >| 

Posts by month

November 2023 (1)
October 2023 (0)
April 2023 (1)
October 2022 (1)
August 2022 (2)
July 2022 (1)
December 2021 (1)
November 2021 (57)
October 2021 (1)
September 2021 (2)
August 2021 (3)
July 2021 (2)
June 2021 (56)
May 2021 (3)
April 2021 (5)
March 2021 (64)
February 2021 (55)
January 2021 (57)
December 2020 (55)
November 2020 (53)
October 2020 (52)
September 2020 (44)
August 2020 (40)
July 2020 (38)
June 2020 (38)
May 2020 (34)
April 2020 (30)
March 2020 (29)
February 2020 (30)
January 2020 (23)
November 2019 (24)
October 2019 (21)
September 2019 (22)
August 2019 (18)
July 2019 (18)
June 2019 (23)
May 2019 (23)
April 2019 (23)
March 2019 (23)
February 2019 (27)
January 2019 (27)
December 2018 (26)
November 2018 (26)
October 2018 (26)
September 2018 (27)
August 2018 (27)
July 2018 (26)
June 2018 (29)
May 2018 (21)
April 2018 (20)
March 2018 (18)
February 2018 (20)
January 2018 (20)
November 2017 (17)
October 2017 (15)
September 2017 (14)
August 2017 (13)
July 2017 (18)
June 2017 (16)
May 2017 (14)
April 2017 (15)
March 2017 (17)

Posts by category

Citywide
District A
District B
District C
District D
District E

Posts by project

Algiers
Aubry St
Audubon
Bayou St. John, Fairgrounds, Seventh Ward
Belleville St
Berkeley Dr
bike lanes
Black Pearl
Black Pearl / East Carrollton
Blue & Green Corridors
Bocage
Bourbon
Breakwater Drive
Broad St
Broadmoor
Bullard Ave
Bywater-Marigny
Canal Blvd
Canal St
Central City
Cherokee St
City Park
Community Meeting
Conti
Convention Center Blvd
Curran Blvd
Desire
Desire/Gordon Plaza
East Riverside/Garden District/Irish Channel/St. Thomas
Filmore
Fleur de Lis
Fontainebleau
Fountainebleau
French Quarter
Freret
Gentilly Resilience District
Gentilly Terrace
Gravier St
Green Infrastructure
Hagan Lafitte
Henry Clay
Hollygrove
Hollygrove, Leonidas
Infrastructure Industry Day
Jackson Ave
Joe Brown Park Bridge
Lacour Monique and Eton St.
Lafitte Corridor Greenway
LAKE TERRACE AND OAKS
Lake Vista
Lakeshore
Lakeview
Lakewood
Little Woods
Lower Ninth Ward
Magazine
Magnolia Bridge
Maintenance Improvements
Marconi
Marleyville-Fontainebleau
Maurepas St and Mystery St
Max Pave II
Message from the Mayor
Michoud Blvd
Mid City
Milneburg
Mirabeau Water Garden
Moving New Orleans Bikes
Navarre
New Aurora
New Orleans East
North Claiborne
Oak Park
Octavia Street
Old Spanish Trail
Pilotland
Pines Village
Pittari St.
Plum Orchard / West Lake Forest
Pontchartrain Park
Pontilly
Read Blvd
Resilience
S Galvez
Safe Routes to School
Saratoga Square
St Claude
St Louis Canal
St. Ann
St. Bernard
St. Charles
St. Roch
Streetscape
SWB
Taft Place
Traffic Advisory
Treme-Lafitte
Viavant-Lake Catherine
Village de L’Est
West Bank
West End
Wisner Bridge
Wright Rd
Youth Study Streets


Looking for work?

The City of New Orleans and the Sewerage & Water Board are hiring.

Find jobs with the City

Find jobs with S&WB

Connect to First Source


Contact us

You can contact us directly at roadwork@nola.gov
or by phone at (504) 658-ROAD (7623).