The Mid City Group A project is approaching 75 percent completion. Hard Rock Construction crews will continue roadway paving and sidewalk operations on Palmyra, Dalcedo, Lopez and S. Gayoso streets throughout the month October. They also plan to complete all water line work in coming weeks.