September 30, 2020 | Category: District D | Tagged as: Milneburg
Command Construction crews are continuing to install new water lines and hope to have all utility work in the project footprint completed by October. Entergy is also working in the area relocating gas lines. Construction started in late July and is expected to be complete in fall 2021, weather permitting. Scope of work for the $17.5M Milneburg Group A project may include:
August 31, 2020 | Category: District D | Tagged as: Milneburg
Command Construction crews continue installing new waterlines on streets throughout the Milneburg Group A project area. Construction, which began in late July, is expected to be complete in fall 2021, weather permitting.
July 31, 2020 | Category: District D | Tagged as: Milneburg
Command Construction crews mobilized for construction on the Milneburg Group A project July 20. The project was delayed due to added scope and re-routing of Entergy gas lines in the project area. Construction is expected to be complete in fall 2021, weather permitting.
June 30, 2020 | Category: District D | Tagged as: Milneburg
Construction on the Milneburg Group A project was delayed so that the contractor could inspect underground sewer and water lines to confirm blockages or breaks in the system. Work is now anticipated begin in July and expected to be complete in late summer / early fall 2021, weather permitting.
May 29, 2020 | Category: District D | Tagged as: Milneburg
Construction on the Milneburg Group A project is slated to begin the week of June 1, 2020, and is expected to be complete in summer 2021, weather permitting. Scope of work for the $17.5M Milneburg Group A project may include:
The City of New Orleans and the Sewerage & Water Board are hiring.
Find jobs with the City
Find jobs with S&WB
Connect to First Source
You can contact us directly at roadwork@nola.gov or by phone at (504) 658-ROAD (7623).