January 23, 2019 | Category: District B | Tagged as: Broad St
The Department of Public Works’ construction contractors are approximately 46 percent complete implementing the S. Broad Street Improvement Project between Erato Street and Tulane Avenue.
December 19, 2018 | Category: District B | Tagged as: Broad St
The Department of Public Works’ construction contractors are approximately 45 percent complete constructing the S. Broad Street Improvement Project between Erato Street and Tulane Avenue.
November 30, 2018 | Category: District B | Tagged as: Broad St
The Department of Public Works’ construction contractors are approximately 15 percent complete constructing the S. Broad Street Improvement Project between Erato Street and Tulane Avenue.
October 5, 2018 | Category: District B | Tagged as: Broad St
The Department of Public Works’ construction contractors have begun making repairs and accessibility improvements to S. Broad Street between Erato Street and Tulane Avenue. The project will last through February of 2019.
September 21, 2018 | Category: District B | Tagged as: Broad St
Starting this month and continuing through February 2019, the Department of Public Works’ construction contractors will begin making repairs and accessibility improvements to Broad Street between Erato Street and Tulane Avenue.
The City of New Orleans and the Sewerage & Water Board are hiring.
Find jobs with the City
Find jobs with S&WB
Connect to First Source
You can contact us directly at ose@nola.gov or by phone at (504) 658-7623.
This website uses cookies to ensure you get the best experience. By using our website, you agree to our cookie policy.