April 24, 2019 | Category: District A | Tagged as: Fleur de Lis
Mayor LaToya Cantrell, City and State officials, as well as neighborhood leaders celebrated completion of the Fleur de Lis Drive Phase III Reconstruction Project with a ribbon cutting ceremony this month.
March 26, 2019 | Category: District A | Tagged as: Fleur de Lis
Command Construction Industries, LLC crews are now 98 percent complete with the Fleur de Lis Drive Phase III Reconstruction Project between 30th Street and Old Hammond Highway in the West End neighborhood.
March 6, 2019 | Category: District A | Tagged as: Fleur de Lis
Command Construction Industries, LLC crews are now 96 percent complete with the Fleur de Lis Drive Phase III Reconstruction Project between 30th Street and Old Hammond Highway in the West End neighborhood.
January 23, 2019 | Category: District A | Tagged as: Fleur de Lis, Lakeview
Command Construction Industries, LLC crews are now 90 percent complete with the Fleur de Lis Drive Phase III Reconstruction Project between 30th Street and Old Hammond Highway in the West End neighborhood.
December 19, 2018 | Category: District A | Tagged as: Fleur de Lis
Command Construction Industries, LLC crews are now 88 percent complete with the Fleur de Lis Drive Phase III Reconstruction Project between 30th Street and Old Hammond Highway in the West End neighborhood.
The City of New Orleans and the Sewerage & Water Board are hiring.
Find jobs with the City
Find jobs with S&WB
Connect to First Source
You can contact us directly at ose@nola.gov or by phone at (504) 658-7623.
This website uses cookies to ensure you get the best experience. By using our website, you agree to our cookie policy.