November 22, 2019 | Category: District D | Tagged as: Little Woods
Command Construction, LLC, crews continue work on water and sewer line replacements throughout the Little Woods Group A project. This work includes rebuilding manholes and videoing existing drain lines to ensure that they are clear and functioning properly.
October 30, 2019 | Category: District E | Tagged as: Little Woods
Command Construction, LLC, crews are working on sewer line replacements throughout the Little Woods Group A project. Water line replacements have been successfully completed throughout the project – including a section of line on W. Tamaron Boulevard.
September 30, 2019 | Category: District E | Tagged as: Little Woods
The Little Woods Group A Patch, Mill, Overlay and Incidental Road Repair project began in September. This $14M project was designed by MSSM Engineering, LLC and is being constructed by Command Construction, LLC.
August 28, 2019 | Category: District E | Tagged as: Little Woods
The Little Woods Group A project began this month with a groundbreaking ceremony. This $14M project was designed by MSSM Engineering, LLC and was awarded to Command Construction, LLC.
July 18, 2019 | Category: District E | Tagged as: Little Woods
The Little Woods Group A project is set to break ground in early August. This $14M project was designed by MSSM Engineering, LLC and will be constructed by Command Construction, LLC.
The City of New Orleans and the Sewerage & Water Board are hiring.
Find jobs with the City
Find jobs with S&WB
Connect to First Source
You can contact us directly at roadwork@nola.gov or by phone at (504) 658-ROAD (7623).