Durr Heavy Construction, LLC crews are 20 percent finished with the Westbank Group A project scope. Crews are currently working in the Whitney neighborhood. The majority of the damaged concrete panels planned to be removed as part of this contract are complete. Asphalt paving work continues this month, while concrete crews are removing frames on newly installed Americans with Disabilities Act-compliant curb ramps and sidewalks. Construction crews will next move to the Algiers Point and McDonogh neighborhoods to perform similar scopes of work.