City contractor Hard Rock Construction, LLC has reached 90 percent complete on the $2.3 million Lakeview North Group A Project.
FEMA has approved additional work that will promote positive drainage, as well as address sidewalk and roadway subsidence that was not included in the original plans. The additional areas of construction will extend the by four months into summer 2018.
This project is designed to correct multiple roadway concerns and the scope of work varies block by block but will include the following:
- Patch Mill / Overlay: Repaving the asphalt roadway from curb to curb and repairing damaged sidewalks;
- Patch Concrete: Removing damaged portions of the concrete roadway and replacing it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replacing it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
Details of the construction sequencing and timeline were first made available at the pre-construction public meeting. View a copy of the public meeting presentation and details about construction sequencing here. To be added to the project contact list, please e-mail RoadWork@nola.gov.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).