The $4.5M Canal Boulevard Full Depth Reconstruction Project, designed by Integrated Logistical Support, Inc. and awarded to Palmisano Construction, continues with the relocation of Entergy’s underground utility lines. Once this process is complete, Palmisano crews will begin excavation of the area. Construction is expected to begin this summer.
View a copy of the presentation given at the November public meeting here. To be added to the project contact list, and to track our progress, visit RoadWork.nola.gov.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).