Construction on the Hollygrove, Leonidas Group A project began the week of April 13, 2020, with crews completing sewer point repairs on Live Oak, Stroelitz, Palm, General Ogden and Hollygrove streets.
The scope of work for the $15M infrastructure improvement project may include: replacing/repairing damaged underground water, sewer and/or drainage lines; repairing damaged curbs and gutters; patching the roadway with asphalt; replacing damaged sidewalks and driveway aprons; and installing Americans with Disabilities Act (ADA)- compliant curb ramps at intersections.
Waggoner Engineering Inc. is the project designer, and Command Construction, LLC, is the contractor. The project is funded by the Federal Emergency Management Agency (FEMA).
View the preconstruction public meeting presentation here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).