Construction continues under the Morrison Canal Bridge at Morrison and Mayo roads. This is the first of three New Orleans East bridges to undergo refurbishment.
Construction contractor, Durr Heavy Construction, LLC, began work on the in May and the $753,000 city-funded project also includes the Citrus Canal Bridge at Lake Forrest, and the Benson Canal Bridge at Lake Forrest.
The scope of work for this project may include: repairing damaged bridge pilings; replacing decking, beams, and other structural components; and installing permanent pavement striping and signage.
Weather permitting, the project is slated for completion in November 2019.