More blocks within the $6.3M Treme-Lafitte Group A project area saw lots of activity in August, as crews began removal of the roadway surface in the 2000- 2400 blocks of St. Philip, Governor Nichols, and North Johnson streets. After completing the road excavation, workers began installing a new base course and a new layer of asphalt.
The scope of work for this City of New Orleans and Sewerage & Water Board of New Orleans joint infrastructure project may include:
- Replacing/repairing damaged underground water, sewer and/or drainage lines
- Repairing damaged curbs and gutters;
- Patching the roadway with asphalt;
- Repaving the asphalt roadway from curb-to-curb;
- Replacing damaged sidewalks and driveway aprons; and
- Installing Americans with Disabilities Act (ADA) compliant curb ramps at intersections.
The project is scheduled for completion in early 2021.
Information about this project was made available at a pre-construction public meeting held March 11, 2020. Access the presentation here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).