Hard Rock Construction crews are continuing work on a $2.2M full depth reconstruction project in the 800 block of St. Ann Street. The fencing around the block remains in place with the roadway closed to vehicular traffic; sidewalks are open to pedestrian traffic.
The intersection of Dauphine and St. Ann streets was temporarily reopened on July 24 while the intersection of Bourbon and St. Ann streets is closed to accommodate utility upgrades and repairs. The intersection is scheduled to reopen to vehicular traffic during the week of September 7. Once that happens, crews will close the Dauphine and St. Ann intersection for approximately two more weeks to resolve a utility conflict. The entire project is scheduled to be completed in September 2020, weather permitting. To date, crews have installed a new, upsized 24-inch drain line, new water line and new sewer line.
Questions about this project should be directed to 504.658.ROAD (7623) or roadwork@nola.gov.