The Department of Public Works’ construction contractor, Hard Rock Construction, LLC has demobilized construction crews from the Desire neighborhood. Designed by Phoenix Global Engineering and Construction, Inc., this contract will be re-packaged into one larger infrastructure improvement project in the future.
Crews were able to complete approximately $500,000 worth of infrastructure improvements prior to demobilization.
The scope of work varied by block but included:
- Patch Mill / Overlay: Repaving the asphalt roadway from curb to curb and repairing damaged sidewalks;
- Patch Concrete: Removing damaged portions of the concrete roadway and replacing it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replacing it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
To be added to the project contact list, visit Roadwork.nola.gov.