The $2.8M Lake Vista Group A project began construction in June 2020. Designed by C & S Consultants, Inc., the project is being constructed by Roubion Roads and Streets, LLC, and continues to make great progress. In the coming month, construction is expected to continue its improvements of the Lake Vista neighborhood infrastructure with a focus on Dove, Marconi, Plover, and Snipe streets.
Click here to view a map of all planned work on the project. The scope of work varies by block and includes the following types of work:
- Patch Mill/Overlay: Repaving the asphalt roadway from curb to curb and repair damaged sidewalks;
- Patch Concrete: Removing damaged portions of the concrete roadway and replace it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replace it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
The City of New Orleans hosted a virtual community meeting via Webex in May 2020 to discuss anticipated impacts to the community. View a copy of the presentation here. To be added to the project contact list and track our progress, visit roadwork.nola.gov.