A $3M full road reconstruction project is slated to start in early 2021 in New Orleans East. Scope of work for the Old Spanish Trail (Nighthart St. - Sherwood Dr.) varies by block but will include:
- Repaving the asphalt and concrete roadway from curb-to-curb in some areas;
- Patching the roadway with asphalt in some areas;
- Repairing some damaged sidewalks and driveway aprons;
- Installing American with Disability Act-compliant curb ramp at intersections; and
- Replacing/repairing damaged underground water lines.
A virtual community meeting that details the project will be held in January 2021. For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).