The City has completed its design of a $4.3M full-depth reconstruction (replacement of roadway and underground utilities) project on Conti Street (600 and 700 blocks) between Bourbon and Chartres streets. City Maintenance Contractor Hard Rock Construction, LLC will begin installing a fence around the roadway for construction in March.
Entergy Gas and Entergy Electric are wrapping up upgrades to their 700 block utilities in advance of the city's work to minimize conflicts during construction and potential delays. Entergy Gas and Electric have already begin to move their crews and operations into the 600 block.
The entire project is expected to take approximately 12 months to complete, weather permitting.
Questions about this project or our Capital Improvement Program should be directed to RoadworkNOLA at 504.658.ROAD (7623) or roadwork@nola.gov.