January 23, 2019 | Category: District D | Tagged as: LAKE TERRACE AND OAKS
The $2.5M Lake Terrace Group A Incidental Road Repair project is currently 88 percent complete with the overall project (including design) and 45 complete with construction.
January 23, 2019 | Category: District D | Tagged as: Gentilly Terrace
The Gentilly Terrace Group A project has moved into the substantial completion phase, pending the conclusion of work that was added to the original scope. City of New Orleans contractor Roubion Shoring & Construction crews are in the process of fully reconstructing the roadway on Acacia Street.
January 23, 2019 | Category: District D | Tagged as: Canal Blvd
A pre-construction public meeting was held on November 26, 2018, to discuss the upcoming Canal Boulevard Full Depth Reconstruction Project.
January 23, 2019 | Category: District D | Tagged as: Filmore
Command Construction Industries, LLC is scheduled to begin working on the Filmore North Group A contract in early February 2019. The contract award was delayed due to a contract protest.
January 23, 2019 | Category: District C, District D | Tagged as: St Claude
The St. Claude Group A Project was designed by Rahman and Associates, Inc. and is being built by Hard Rock Company, LLC. The $8-9 million project is scheduled to begin in February 2019 and estimated to be completed by the spring 2019.
The City of New Orleans and the Sewerage & Water Board are hiring.
Find jobs with the City
Find jobs with S&WB
Connect to First Source
You can contact us directly at roadwork@nola.gov or by phone at (504) 658-ROAD (7623).