The $2.5M Lake Terrace Group A Incidental Road Repair project is currently 88 percent complete with the overall project (including design) and 45 complete with construction.
Palmisano Construction crews recently completed roadway paving (allowing residents access to their driveways) throughout the project’s limits and have begun excavation for milling at intersections.
The project, on schedule to be completed by spring 2019, includes the following scope of work:
- Patching the roadway with asphalt;
- Replacing damaged portions of concrete with new, level concrete;
- Repairing damaged curbs and gutters;
- Repairing damaged sidewalks and driveway aprons;
- Installing Americans with Disabilities Act-compliant curb ramps at intersection; and
- Replacing/repairing damaged underground water, and drainage lines.
The City hosted a pre-construction public meeting to discuss the project’s construction sequencing and anticipated impacts. View a copy of the meeting presentation here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).