The St. Claude Group A project was designed by Rahman and Associates Inc. and is being built by Hard Rock Construction Company LLC. There is an estimated $1M in added scope on the $3.8M project, which is scheduled to be completed in early spring.
Crews continue to focus on upgrading drainage systems on Independence and N. Roman streets. Roadway will be completed on N. Roman, Marais, Bartholomew and France streets.
The scope varies by block but includes the following types of work:
- Patch Mill/Overlay: Repaving the asphalt roadway from curb to curb and repair damaged sidewalks;
- Patch Concrete: Removing damaged portions of the concrete roadway and replace it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replace it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
Learn more about the project’s construction sequencing and anticipated impacts by viewing a copy of the public meeting presentation here.