Wallace C. Drennan crews continue work on the Lower Ninth Ward Northwest Group B project. Crews are currently installing water lines on Reynes Street from N. Derbigny Street to Tonti Street. Residents will continue to be notified ahead of any work that will impact their access and utilities.
This $5.7M project, designed by Burk–Kleinpeter Inc. varies block by block but includes the following:
• Installation of new subsurface drainage, sewer, and water lines;
• Removal and replacement of sidewalks and driveways aprons;
• Installation of Americans with Disabilities Act-compliant curb ramps at intersections;
• Manhole adjustments; and
• Repaving of the roadway.
Details of this project were made available at the pre-construction public meeting. View a copy of the public meeting presentation here.