In January, crews continued working on sewer and drain lines along East Laverne Street and performed water line work on Stemway Drive. Additional scope will be included as part of the project on Stemway Drive between Chef Menteur Highway and Warfield Street. The roadway was originally scheduled for incidental road repairs but it was determined that road conditions merited pavement replacement and milling overlay by the Warfield Street intersection. The project is estimated to be completed in late 2021, weather permitting.
The $18.2M Pines Village Group A project was designed by All South Consulting Engineers, Inc., and the scope of work varies block by block but may include the following:
- Repaving the asphalt roadway from curb-to-curb;
- Patching the roadway with asphalt;
- Repairing damaged sidewalks and driveway aprons;
- Installing Americans with Disabilities Act-compliant curb ramps at intersections;
- Replacing / repairing damaged underground water, sewer and / or drainage lines.
Access the presentation from the public pre-construction meeting here. For more information about this project and other upcoming work, please visit roadwork.nola.gov or call 504.658.ROAD (7623).