Hard Rock Construction Co., LLC crews continue to install new and improved water line systems to replace the 70+ year-old systems currently in place. This month crews will begin to install new water line systems on Prentiss Avenue, Odin Street, and Athis Court. Residents who live on certain blocks along Mendez Street, Debore Drive, Madrid Street, Feliciana Street, and Montegut Street have received new concrete roadways and curbs as part of the project. Additionally, crews are scheduled to continue concrete roadway pours on blocks of Pauline Street.
Residents will continue to be informed ahead of any work that will involve utility disruption and / or impact their parking and access to their streets.
This $10M project was designed by Stanley Consultants. As a full-depth reconstruction project, work varies block by block but includes:
- Repaving asphalt roadway from curb-to-curb;
- Repairing damaged sidewalks and driveway aprons;
- Installing Americans with Disabilities Act-compliant curb ramps at intersections; and
- Replacing / repairing damaged underground water, sewer, and / or drainage lines.
Information about this project was made available at a pre-construction public meeting on September 22, 2020. The presentation can be found here. For more information about this project and other upcoming work, please visit roadwork.nola.gov or call 504.658.ROAD (7623).