Command Construction Industries, LLC is scheduled to begin work on the Treme-Lafitte Group B full-depth reconstruction project in February 2021, which is an updated notice to proceed (NTP) from the original October 2020 time period.
Once the project starts, we will inform residents ahead of any work that will involve utility disruptions and / or impact parking and access to their street.
This $8M project was designed by Meyers Engineering, LTD; the scope of work varies block by block but includes the following:
- Resurfacing the roadway with asphalt or concrete;
- Repairing damaged curbs;
- Repairing damaged sidewalks and driveway aprons;
- Installing Americans with Disabilities Act-compliant curb ramps at intersections; and
- Replacing / repairing damaged underground water, and drainage lines.
View a copy of the presentation given at the September 10, 2020, public meeting here. For more information about this project and other upcoming work, please visit roadwork.nola.gov or call 504.658.ROAD (7623).