This month, Command Construction Industries, LLC crews, in close collaboration with the Sewerage and Water Board New Orleans, resumed water line work on the Little Woods Group A infrastructure improvement project. In addition to water line work, the Department of Public Works (DPW) and its inspectors continued pre-pour inspections. These inspections ensure everything is properly constructed prior to placement of the final layer of concrete or asphalt. Roadway paving operations are set to be completed this month, including the areas of Lake Carmel, Lehigh, Morrison and Yardley streets.
Residents will be notified of work that will impact their access and / or cause disruption to their utilities.
The scope of this $14M patch, mill, overlay and incidental road repairs project varies by block but includes:
- Repaving the asphalt roadway from curb-to-curb;
- Patching the roadway with asphalt or concrete;
- Repairing damaged sidewalks and driveway aprons;
- Installing Americans with Disabilities Act-compliant curb ramps at intersections; and
- Replacing / repairing damaged underground water, sewer, and/or drainage lines.
Details of this project were first made available at the pre-construction public meeting. View a copy of the public meeting presentation and details about construction sequencing here.
For more information about this project and other upcoming work, please visit roadwork.nola.gov or call 504.658.ROAD (7623).