City of New Orleans contractor Hard Rock Construction, LLC began work on the Lakewood Group A Patch, Mill, Overlay and Incidental Road Repair project in June. In conjunction with the Sewerage and Water Board of New Orleans, waterlines are currently being replaced on Marcia, Brooks and Harney streets. Residents will continue to be notified in advance of any scheduled, temporary disruptions during this critical phase of the project.
The scope of work for this $1.6M project varies block by block but will include the following:
- Patching the roadway with asphalt;
- Replacing damaged portions of concrete with new, level concrete;
- Repairing damaged curbs and gutters;
- Repairing damaged sidewalks and driveway aprons;
- Installing Americans with Disabilities Act-compliant curb ramps at intersections; and
- Replacing/repairing damaged, underground water and drainage lines.
Details of the construction sequencing and timeline were first made available at the pre-construction public meeting. View a copy of the public meeting presentation and details about construction sequencing here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).