Construction crews are 90 percent complete with water line installations on the Pines Village Group A project. Additionally, crews have completed all drainage work on the project, finished 80 percent of the planned repaving work and have begun installing new sidewalks and driveways. The overall scope of the project also includes installing Americans with Disabilities Ace-compliant curb ramps at intersections.