The $1.6M Lakewood Group A Patch, Mill, Overlay and Incidental Road Repair project will begin this month and is designed to remove damaged portions of the asphalt roadway and replace it with new, smooth pavement. It was designed by Phoenix Global Engineering and Construction, Inc. and is being constructed by Hard Rock Construction, LLC.
The scope of work varies block by block but includes the following:
- Patch Concrete: Removing damaged portions of the concrete roadway and replacing it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replacing it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
Details of the construction sequencing and timeline were first made available at the pre-construction public meeting. View a copy of the public meeting presentation and details about construction sequencing here. To be added to the project contact list, please e-mail RoadWork@nola.gov.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).