Wallace C. Drennan, Inc. crews are making strides in the prevention of stormwater management-related issues by protecting and conducting routine cleaning of catch basins located within construction site activity. The project team is monitoring the management of the stormwater drains and quickly addressing issues that arise.
If residents notice catch basins obstructed with construction materials, please contact RoadworkNOLA at 504.658.ROAD (7623).
We will continue to inform residents ahead of any work that will involve utility disruption and/or impact their parking and access to their street and driveways.
This $10.5M project was designed by Schenk, Endom & Flanagan, LLC. As a full-depth reconstruction project, work varies block by block but includes:
- Repaving asphalt roadway from curb-to-curb;
- Repairing damaged sidewalks and driveway aprons;
- Installing Americans with Disabilities Act (ADA)-compliant curb ramps at intersections; and
- Replacing / repairing damaged underground water, sewer, and drainage lines.
The project began in October 2020 and is expected to be completed in winter 2022, weather permitting.
Information about this project was made available at a public pre-construction meeting. The presentation can be found here. For more information about this project and other upcoming work, please visit roadwork.nola.gov or call 504.658.ROAD (7623).