Command Construction Industries, LLC crews are currently 72 percent complete on the Read Boulevard West Group A project construction. This is the first of two projects planned in the neighborhood.
Work continues on Evangeline, Arthur and Gabriel drives. Residents should expect approximately 21 day-timeframe with limited access to driveways. View the project map noting locations here of planned work in area.
The scope work varies by block but includes the following types of work:
- Patch Mill / Overlay: Repave the asphalt roadway from curb to curb and repair damaged sidewalks;
- Patch Concrete: Remove damaged portions of the concrete roadway and replace it with new smooth concrete pavement;
- Incidental Road Repairs: Remove damaged portions of the asphalt roadway and replace it with new smooth pavement; and
- Non-Paving Incidentals: Repair damaged sidewalks, driveway aprons and curbs within the public right-of-way.
Learn more about the project’s construction sequencing and anticipated impacts by viewing a copy of the public meeting presentation here.