The project team is preparing for final inspection on the Gentilly Terrace Group A project. Roubion Shoring and Construction crews have completed all of the additional work, changes and adjustments outlined by the City’s project managers.
The $2.2M project is scheduled to wrap up by April 1 and included the following types of work:
- Patch Mill / Overlay: Repaving the asphalt roadway from curb to curb and repairing damaged sidewalks;
- Patch Concrete: Removing damaged portions of the concrete roadway and replacing it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replacing it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623)