The $2.5M Lake Terrace Group A Incidental Road Repair project is substantially complete and in the final inspection phase.
Palmisano Construction crews recently completed roadway paving on sections of Lark Street and Elysian Fields Avenue. They are currently working to complete suggested changes and adjustments outlined by the City’s project managers.
The project, on schedule to be completed by spring 2019, included the following scope of work:
- Patching the roadway with asphalt;
- Replacing damaged portions of concrete with new, level concrete;
- Repairing damaged curbs and gutters;
- Repairing damaged sidewalks and driveway aprons;
- Installing Americans with Disabilities Act-compliant curb ramps at intersection; and
- Replacing/repairing damaged underground water, and drainage lines.
The City hosted a pre-construction public meeting to discuss the project’s construction sequencing and anticipated impacts. View a copy of the public meeting presentation here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).