The Department of Public Works’ construction contractors are approximately 96 percent complete implementing the S. Broad Street Improvement Project between Erato Street and Tulane Avenue.
Crews are currently striping the new roadway, which includes a new protected bike lane over the Broad Street overpass and a dedicated bike lane between Broad Street overpass and Tulane Avenue.
The scope of work includes:
- Installing a new traffic signal; (complete)
- Making guardrail and deck improvements; (complete)
- Repairing damaged catch basins; (complete) and
- Adding roadway striping including a protected bike lane over the Broad Street overpass and a dedicated bike lane between the Broad Street overpass and Tulane Avenue; (under way)
- Adding crosswalk striping; (complete)
- Installing new concrete bus islands; (complete) and
- Re-allocating curb space including moving freight and passenger zones. (complete)