City of New Orleans contractor Hard Rock Construction, LLC has begun additional FEMA approved work on Louisville Street as part of the Lakeview South Group A project. This work includes new subsurface utilities at Colbert and Kenilworth streets designed to level the roadway and improve drainage. The work is expected to be complete by early summer 2019.
The $5.9M Patch, Mill, Overlay and Incidental Road Repair project was designed by Richard C. Lambert Consultants, LLC.
The scope of work varies block by block but includes the following:
- Patch Concrete: Removing damaged portions of the concrete roadway and replacing it with new smooth concrete pavement; and
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replacing it with new smooth pavement.
Details of the construction sequencing and timeline were first made available at the pre-construction public meeting. View a copy of the public meeting presentation and details about construction sequencing here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).