In order to establish better drainage, City of New Orleans contractor, Beverly Construction will begin work on an ehhanced redesign for several streets on the West End Group A project. Regent and Hay streets are a part of this redesign and work is expected to begin by summer 2020. With the redesign and added scope, this project is now extended until fall 2020.
This $5.6M project was designed by Atkins, LLC. , Inc. The scope of work varies block by block but includes the following:
- Patching the roadway with asphalt or concrete;
- Replacing damaged portions of concrete with new, level concrete;
- Repairing damaged curbs and gutters;
- Repairing damaged sidewalks and driveway aprons;
- Installing Americans with Disabilities Act-compliant curb ramps at intersection; and
- Replacing/repairing damaged underground water, and drainage lines.
View a copy of the presentation given at the January public meeting here. To be added to the project contact list, and to track our progress, visit RoadWork.nola.gov.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).