Hard Rock Construction Co., LLC is moving toward street construction on Charlotte Drive and working to replace and repair utility lines in the $4.2M Filmore North Group B project. This project will greatly benefit the Upper Gentilly neighborhood by providing better drainage and roads for residents. The project is expected to be complete this summer.
Click here to view a map of the project. The scope of work, which is approximately 40 percent complete, varies by block and includes:
- Patch Mill/Overlay: Repaving the asphalt roadway from curb to curb and repair damaged sidewalks;
- Patch Concrete: Removing damaged portions of the concrete roadway and replace it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replace it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
The City of New Orleans held a public meeting about the project in June 2020 to discuss anticipated impacts to the community. View a copy of the meeting presentation here. For more information about this project and other upcoming work, please visit roadwork.nola.gov or call 504.658.ROAD (7623).