Hard Rock Construction crews, in close collaboration with Department of Public Works and Sewerage and Water, continue preparing the Freret Group A project for substantial completion. Upon completion of punch list items project team will complete final inspections in April.
Residents will continue to be informed ahead of any work that will involve utility disruption and/or impact their parking and access to their streets.
This $4M project was designed by Kyle Associates, LLC. The scope of work varies block by block but includes the following:
- Repaving the asphalt roadway from curb-to-curb;
- Patching the roadway with asphalt or concrete; and
- Repairing damaged sidewalks and driveway aprons.
Details of the original construction sequencing and timeline were first made available at the public pre-construction meeting. View a copy of the meeting presentation and details about construction sequencing here.
For more information about this project and other upcoming work, please visit roadwork.nola.gov or call 504.658.ROAD (7623).