Latest News

District C

Traffic Advisory: City, SWBNO to Begin Major Infrastructure Upgrades on Conti Street Between Bourbon and Chartres streets

March 12, 2021   |    Category: District C    |   Tagged as: Conti, Traffic Advisory

Traffic Advisory: City, SWBNO to Begin Major Infrastructure Upgrades on Conti Street Between Bourbon and Chartres streets

The City of New Orleans, Department of Public Works and Sewerage and Water Board of New Orleans today announced that they will begin a $4.3 million full-depth reconstruction (replacement of the roadway and underground utilities) project beginning at 8 a.m. on Monday, March 15, weather permitting. Hard Rock Construction, LLC crews will install fencing around the 700 block of Conti Street roadway between Bourbon and Royal streets and close the block to vehicular traffic. Public safety is our priority; all businesses will remain open and accessible throughout construction.


“We are very excited to begin this much-needed project and to improve upon the great work that was done with the Bourbon Phase 2 project,” said Deputy Chief Administrative Officer for Infrastructure Ramsey Green. “We are upsizing the drainage, rehabilitating the sewer system and improving the overall quality of life with new, smooth pavement. And we are approaching this project with safety, accessibility and comfort in mind. As we continue, we look forward to learning from both residents and businesses alike to ensure our work enhances the beauty of the French Quarter and creates an overall healthier environment.”


Design Elements

The scope of work calls for removing and replacing the existing pavement, replacing and upsizing the existing drain lines and catch basins, replacing the existing water lines, repairing and/or replacing the existing sewer lines, replacing the existing low-pressure gas lines with high pressure gas lines, replacing and/or repairing the existing underground electrical duct banks, replacing sidewalks and adding Americans with Disabilities Act (ADA)-compliant curb ramps at intersections and a mid-block crossing at Exchange Place, as well as bollards the length of the block on the Esplanade side/4th Circuit Supreme Court.


Lessons Learned

The project team has incorporated lessons learned from the Bourbon Phase 2 project into the framework for work on Conti Street.

  • Exploratory Trenching: As part of the plan and design process, the contractor completed exploratory trenching to identify the actual locations of the utilities beneath the ground to help prevent schedule delays during construction.
  • Storage of Materials: Construction supplies will be stored offsite outside of the French Quarter (expect more traffic from deliveries).
  • Contractor Parking: The contractor is only permitted to have 10 vehicles parked in the vicinity of the construction. All other vehicles must be parked outside of the French Quarter.
  • Entergy Working in Advance: Additionally, Entergy Gas and Entergy Electric are working in advance of the City’s project to minimize conflicts and associated delays. Both Entergy Gas and Entergy Electric recently completed their utility upgrades in the 700 block and have shifted their crews into the 600 block.

Work Plan and Closures

Hard Rock crews will continue with a seven-day work week from 8 a.m. until sunset each day. Once construction is completed in the 700 block of the Conti roadway (anticipated in June 2021), the fence will be removed, and work will begin on sidewalks. When all construction has been completed in the 700 block and Entergy Gas/Entergy Electric crews have wrapped up their upgrades in the 600 block of Conti Street, Hard Rock crews will shift their operations into the 600 block roadway between Royal and Chartres streets.

  • Full Roadway Closure: 700 block of Conti Street will be closed to vehicular traffic beginning at 8 a.m. on Monday, March 15, and remain closed through the duration of construction on this block. Commuters are advised to detour from Bourbon Street onto Toulouse Street and then onto Royal Street.
  • Workday Closure: 600 block of Conti Street will be intermittently closed to vehicular traffic daily while Entergy Gas and Entergy Electric crews are upgrading their utilities. Intermittent closures will continue through the duration of the project. During the day, commuters are advised to detour from Bourbon Street onto Toulouse Street and then onto Decatur Street. The 600 block will reopen to vehicular traffic each night.
  • Temporary Closure: 300 block of Chartres Street will be closed to vehicular traffic daily while Entergy Electric crews perform work at the intersection of Conti and Chartres streets. During the day, commuters are advised to detour from Bienville Street onto Bourbon Street onto Toulouse Street and then onto Decatur Street. The 300 block will reopen to vehicular traffic each night.
  • Future Intersection Closure: At some point during the project, the intersection of Royal and Conti streets will be closed to accommodate utility upgrades. A traffic advisory will be sent ahead of that closure.

Timeline and Project Participants

The project, which was designed by Mott McDonald, LLC and is being constructed by Hard Rock Construction, LLC is anticipated to run through winter 2021 (approximately four months per block). Project partners include Entergy Electric, Entergy Gas, Cox Communications and AT&T.


Questions about this project or our Capital Improvement Program should be directed to 504.658.ROAD (7623) or roadwork@nola.gov.


ABOUT ROADWORKNOLA

The City of New Orleans Department of Public Works (DPW) and Sewerage and Water Board of New Orleans (SWBNO) are working together to implement an unprecedented program to restore our damaged infrastructure. Using local and federal funds, the $2.3 billion program is the most comprehensive that our region has seen in a generation.

 

WHAT YOU SHOULD KNOW ABOUT ROADWORKNOLA

  • More than $2.3 billion worth of DPW/SWBNO work across the City
  • Nearly 200 individual projects – every neighborhood will feel this positive impact
  • Project schedules coordinated to minimize construction-related impacts
  • Economic opportunity for the City’s small and disadvantaged businesses
  • Proactive communications so that residents are well informed throughout the program

 

See Traffic Advisory here: City, SWBNO to Begin Major Infrastructure Upgrades on Conti Street Between Bourbon & Chartres Streets (govdelivery.com)

Add to Twitter Add to Facebook Add to LinkedIn Add to Reddit

Posts by month

November 2023 (1)
October 2023 (0)
April 2023 (1)
October 2022 (1)
August 2022 (2)
July 2022 (1)
December 2021 (1)
November 2021 (57)
October 2021 (1)
September 2021 (2)
August 2021 (3)
July 2021 (2)
June 2021 (56)
May 2021 (3)
April 2021 (5)
March 2021 (64)
February 2021 (55)
January 2021 (57)
December 2020 (55)
November 2020 (53)
October 2020 (52)
September 2020 (44)
August 2020 (40)
July 2020 (38)
June 2020 (38)
May 2020 (34)
April 2020 (30)
March 2020 (29)
February 2020 (30)
January 2020 (23)
November 2019 (24)
October 2019 (21)
September 2019 (22)
August 2019 (18)
July 2019 (18)
June 2019 (23)
May 2019 (23)
April 2019 (23)
March 2019 (23)
February 2019 (27)
January 2019 (27)
December 2018 (26)
November 2018 (26)
October 2018 (26)
September 2018 (27)
August 2018 (27)
July 2018 (26)
June 2018 (29)
May 2018 (21)
April 2018 (20)
March 2018 (18)
February 2018 (20)
January 2018 (20)
November 2017 (17)
October 2017 (15)
September 2017 (14)
August 2017 (13)
July 2017 (18)
June 2017 (16)
May 2017 (14)
April 2017 (15)
March 2017 (17)

Posts by category

Citywide
District A
District B
District C
District D
District E

Posts by project

Algiers
Aubry St
Audubon
Bayou St. John, Fairgrounds, Seventh Ward
Belleville St
Berkeley Dr
bike lanes
Black Pearl
Black Pearl / East Carrollton
Blue & Green Corridors
Bocage
Bourbon
Breakwater Drive
Broad St
Broadmoor
Bullard Ave
Bywater-Marigny
Canal Blvd
Canal St
Central City
Cherokee St
City Park
Community Meeting
Conti
Convention Center Blvd
Curran Blvd
Desire
Desire/Gordon Plaza
East Riverside/Garden District/Irish Channel/St. Thomas
Filmore
Fleur de Lis
Fontainebleau
Fountainebleau
French Quarter
Freret
Gentilly Resilience District
Gentilly Terrace
Gravier St
Green Infrastructure
Hagan Lafitte
Henry Clay
Hollygrove
Hollygrove, Leonidas
Infrastructure Industry Day
Jackson Ave
Joe Brown Park Bridge
Lacour Monique and Eton St.
Lafitte Corridor Greenway
LAKE TERRACE AND OAKS
Lake Vista
Lakeshore
Lakeview
Lakewood
Little Woods
Lower Ninth Ward
Magazine
Magnolia Bridge
Maintenance Improvements
Marconi
Marleyville-Fontainebleau
Maurepas St and Mystery St
Max Pave II
Message from the Mayor
Michoud Blvd
Mid City
Milneburg
Mirabeau Water Garden
Moving New Orleans Bikes
Navarre
New Aurora
New Orleans East
North Claiborne
Oak Park
Octavia Street
Old Spanish Trail
Pilotland
Pines Village
Pittari St.
Plum Orchard / West Lake Forest
Pontchartrain Park
Pontilly
Read Blvd
Resilience
S Galvez
Safe Routes to School
Saratoga Square
St Claude
St Louis Canal
St. Ann
St. Bernard
St. Charles
St. Roch
Streetscape
SWB
Taft Place
Traffic Advisory
Treme-Lafitte
Viavant-Lake Catherine
Village de L’Est
West Bank
West End
Wisner Bridge
Wright Rd
Youth Study Streets


Looking for work?

The City of New Orleans and the Sewerage & Water Board are hiring.

Find jobs with the City

Find jobs with S&WB

Connect to First Source


Contact us

You can contact us directly at roadwork@nola.gov
or by phone at (504) 658-ROAD (7623).