The St. Claude Group A Project was designed by Rahman and Associates, Inc. and is being built by Hard Rock Construction Company, LLC. The $3.9M project is estimated to be complete in one year.
Due to the high river, work on the streets within the project scope and boundaries of St. Claude Avenue - Homer Plessy Way, Burgundy Street and Poland Avenue - is delayed for at least another 30 days. Crews have mobilized north of St. Claude to continue to install Americans with Disabilities Act (ADA) compliant ramps, sidewalks, and driveways on Lesseps Street. Following, asphalt-paving will occur on Desire, Alvar, Lesseps, N. Derbigny and N. Johnson streets.
The scope work varies by block but includes the following types of work:
- Patch Mill / Overlay: Repaving the asphalt roadway from curb to curb and repair damaged sidewalks;
- Patch Concrete: Removing damaged portions of the concrete roadway and replace it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replace it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
Learn more about the project’s construction sequencing and anticipated impacts by viewing a copy of the public meeting presentation here.