Command Construction Industries, LLC is completing waterline tie-ins on Madrid, Burbank, and Athis streets. Once tie-ins are complete, asphalt crews will mobilize.
The estimated budget including engineering, design, geotechnical testing and construction planned in the entire Filmore neighborhood is approximately $67M. This budget is likely to change pending project bids and construction costs.
Designed by Professional Engineering Consultants Corporation (PEC), the first project will include a variety of work that varies by block and includes some waterline replacements:
- Patch Mill / Overlay: Repaving the asphalt roadway from curb to curb and repair damaged sidewalks;
- Patch Concrete: Removing damaged portions of the concrete roadway and replace it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replace it with new smooth pavement; and
- Non-Paving Incidentals: Repairing damaged sidewalks, driveway aprons and curbs within the public right-of-way.
The City hosted a pre-construction community meeting in January 2019 to discuss anticipated construction impacts. View a copy of the presentation here. To be added to the project contact list, and to track our progress, visit RoadWork.nola.gov.