Wallace C. Drennan Inc. crews are continuing to make progress on the Pines Village Group A project. Completion of waterline installations is at 40 percent, sewer line work is at 75 percent and pavement restoration is at 35 percent. The overall scope of the project also includes repairing damaged sidewalks and driveway aprons; and installing Americans with Disabilities Act-compliant curb ramps at intersections.
The approximately $12.7M project was designed by All South Consulting Engineers Inc., and is estimated to be complete in the fall of 2022, weather permitting.
Access the presentation from the public pre-construction meeting here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).