City of New Orleans contractor Hard Rock Construction, LLC has now completed 86 percent of the concrete paving for the Lakeview South Group A project. Crews are expected to complete all concrete paving in December, weather permitting. In addition, crews have also completed a substantial amount of asphalt milling and removal.
The $5.9M Patch, Mill, Overlay and Incidental Road Repair project is designed to remove damaged portions of the asphalt roadway and replace it with new, smooth pavement. The project was designed by Richard C. Lambert Consultants, LLC.
The scope of work varies block by block but includes the following:
- Patch Concrete: Removing damaged portions of the concrete roadway and replacing it with new smooth concrete pavement;
- Incidental Road Repairs: Removing damaged portions of the asphalt roadway and replacing it with new smooth pavement; and
The overall project is 27 percent complete. Details of the construction sequencing and timeline were first made available at the pre-construction public meeting. View a copy of the public meeting presentation and details about construction sequencing here.
For more information about this project and other upcoming work, please visit Roadwork.nola.gov or call 504.658.ROAD (7623).