The Department of Public Works’ construction contractors are approximately 15 percent complete constructing the S. Broad Street Improvement Project between Erato Street and Tulane Avenue.
Crews are currently framing new concrete bus islands and repaving damaged portion of roadway. The project is scheduled to last through February of 2019.
The scope of work includes;
- Installing a new traffic signal (underway);
- Making guardrail and deck improvements;
- Repairing damaged catch basins;
- Adding roadway striping including a protected bike lane over the Broad Street overpass and a dedicated bike lane between the Broad Street overpass and Tulane Avenue;
- Adding crosswalk striping;
- Installing new concrete bus islands; and
- Re-allocating curb space including moving freight and passenger zones.
Residents and commuters should expect intermittent travel lane closures during some of the project tasks. Sign up for news releases from Mayor Cantrell’s office here.
The City hosted a public meeting to discuss construction sequencing in September. View a copy of the presentation here. Sign up for project updates by writing RoadWork@nola.gov.