November 22, 2019 | Category: District E | Tagged as: Village de L’Est
Construction on the second project in the Village De L’Est area continues. Crews are working on the north side of Endeavors and Expedition. The project is anticipated to be completed in mid-summer 2020, weather permitting. Learn more about the project by viewing a copy of the public meeting presentation here.
November 22, 2019 | Category: District E | Tagged as: Read Blvd
Command Construction Industries, LLC crews continue to work on the remaining curbs and roadway patches throughout the Read Boulevard West Group A project. This is the first of two projects planned in the neighborhood.
November 22, 2019 | Category: District D | Tagged as: Filmore
The $4.4M Filmore South Group A project was designed by Volkert, Inc. and is being constructed by Hard Rock Construction, LLC. The project is tentatively scheduled to be completed in fall 2020, weather permitting.
The Filmore North Group A project is currently estimated at $6.5M, with an increase of approximately $2M in scope. Crews continue roadway construction throughout the project area.
November 22, 2019 | Category: District D | Tagged as: St Claude
This $1.5M St. Claude Drainage Improvements Project began on Montegut Street in late October, and the Department of Housing and Urban Development’s (HUD) Community Development Block Grant (CDBG) funded project includes a full street reconstruction.
The City of New Orleans and the Sewerage & Water Board are hiring.
Find jobs with the City
Find jobs with S&WB
Connect to First Source
You can contact us directly at ose@nola.gov or by phone at (504) 658-7623.
This website uses cookies to ensure you get the best experience. By using our website, you agree to our cookie policy.