Latest News

BLACK PEARL/EAST CARROLLTON GROUP A CONTINUES SIGNIFICANT PROGRESS

November 19, 2020   |    Category: District A    |   Tagged as: Black Pearl / East Carrollton

BLACK PEARL/EAST CARROLLTON GROUP A CONTINUES SIGNIFICANT PROGRESS

The $11.9M Black Pearl/East Carrollton Group A project, which began construction in August 2020, continues to make significant progress. Contractor Hard Rock Construction Co., LLC has completed planned sewer repairs on Adams, Birch, Burdette, Fern, Hickory, Huso, Jeanette, Pearl, Plum, Short, and Zimpel streets. That work will continue in the coming month, as well as the beginning of excavation and concrete work.

WORK RESUMES ON BREAKWATER DRIVE

November 19, 2020   |    Category: District A    |   Tagged as: Breakwater Drive

WORK RESUMES ON BREAKWATER DRIVE

TKTMJ crews have resumed work on the Breakwater Drive improvement project. Crews are currently preparing for roadway work, parking lot and pier modifications and relocating the cul-de-sac. With the newly added scope, completion is expected in spring 2021.

WORK TO CONTINUE ON 14th, 20th and 30th STREETS THROUGH THE END OF THE YEAR 

November 19, 2020   |    Category: District A    |   Tagged as: West End

WORK TO CONTINUE ON 14th, 20th and 30th STREETS THROUGH THE END OF THE YEAR 

Beverly Construction, LLC., crews shifted work back to 14th, 20th and 30th in October but will keep small crews on Regent Street on the West End Group A  project. Crews plan to wrap all major work on these blocks at the end of the year. Work is still happening on Regent Street, where additional scope was added in early-November. Waterline and paving efforts on these streets will continue with consideration of the approaching holiday season.  

PAVEMENT RESTORATION AND WATER LINE INSTALLATIONS CONTINUE IN NAVARRE GROUP A PROJECT

November 19, 2020   |    Category: District A    |   Tagged as: Navarre

PAVEMENT RESTORATION AND WATER LINE INSTALLATIONS CONTINUE IN NAVARRE GROUP A PROJECT

Crews tied in a new water line along Canal Boulevard in November, and repavement work throughout the project is progressing. Crews also began removing roadway and installing a new base on Navarre Avenue and at North Park Place and Middle Park Place, and started curb and gutter installation on Charles Place and Middle Park Place. ADA ramps, sidewalks and driveway aprons are being installed on West Park Place, and crews began installing the asphalt binder layer of roadway on Middle Park Place and South Park Place.

SEWER REPAIRS AND PAVEMENT RESTORATION CONTINUE IN HOLLYGROVE, LEONIDAS GROUP A PROJECT

November 19, 2020   |    Category: District A    |   Tagged as: Hollygrove, Leonidas

SEWER REPAIRS AND PAVEMENT RESTORATION CONTINUE IN HOLLYGROVE, LEONIDAS GROUP A PROJECT

Sewer line work continued in November as six crews from Wallace C. Drennan Inc. facilitated sewer repairs in the Hollygrove, Leonidas Group A project area. Additional work crews focused on putting in the binder and wearing layers of asphalt, which are two of the final steps in roadway restoration.

Displaying results 41-45 (of 53)
 |<  <  2 - 3 - 4 - 5 - 6 - 7 - 8 - 9 - 10 - 11  >  >| 
November 2020

Posts by month

November 2023 (1)
October 2023 (0)
April 2023 (1)
October 2022 (1)
August 2022 (2)
July 2022 (1)
December 2021 (1)
November 2021 (57)
October 2021 (1)
September 2021 (2)
August 2021 (3)
July 2021 (2)
June 2021 (56)
May 2021 (3)
April 2021 (5)
March 2021 (64)
February 2021 (55)
January 2021 (57)
December 2020 (55)
November 2020 (53)
October 2020 (52)
September 2020 (44)
August 2020 (40)
July 2020 (38)
June 2020 (38)
May 2020 (34)
April 2020 (30)
March 2020 (29)
February 2020 (30)
January 2020 (23)
November 2019 (24)
October 2019 (21)
September 2019 (22)
August 2019 (18)
July 2019 (18)
June 2019 (23)
May 2019 (23)
April 2019 (23)
March 2019 (23)
February 2019 (27)
January 2019 (27)
December 2018 (26)
November 2018 (26)
October 2018 (26)
September 2018 (27)
August 2018 (27)
July 2018 (26)
June 2018 (29)
May 2018 (21)
April 2018 (20)
March 2018 (18)
February 2018 (20)
January 2018 (20)
November 2017 (17)
October 2017 (15)
September 2017 (14)
August 2017 (13)
July 2017 (18)
June 2017 (16)
May 2017 (14)
April 2017 (15)
March 2017 (17)

Posts by category

Citywide
District A
District B
District C
District D
District E

Posts by project

Algiers
Aubry St
Audubon
Bayou St. John, Fairgrounds, Seventh Ward
Belleville St
Berkeley Dr
bike lanes
Black Pearl
Black Pearl / East Carrollton
Blue & Green Corridors
Bocage
Bourbon
Breakwater Drive
Broad St
Broadmoor
Bullard Ave
Bywater-Marigny
Canal Blvd
Canal St
Central City
Cherokee St
City Park
Community Meeting
Conti
Convention Center Blvd
Curran Blvd
Desire
Desire/Gordon Plaza
East Riverside/Garden District/Irish Channel/St. Thomas
Filmore
Fleur de Lis
Fontainebleau
Fountainebleau
French Quarter
Freret
Gentilly Resilience District
Gentilly Terrace
Gravier St
Green Infrastructure
Hagan Lafitte
Henry Clay
Hollygrove
Hollygrove, Leonidas
Infrastructure Industry Day
Jackson Ave
Joe Brown Park Bridge
Lacour Monique and Eton St.
Lafitte Corridor Greenway
LAKE TERRACE AND OAKS
Lake Vista
Lakeshore
Lakeview
Lakewood
Little Woods
Lower Ninth Ward
Magazine
Magnolia Bridge
Maintenance Improvements
Marconi
Marleyville-Fontainebleau
Maurepas St and Mystery St
Max Pave II
Message from the Mayor
Michoud Blvd
Mid City
Milneburg
Mirabeau Water Garden
Moving New Orleans Bikes
Navarre
New Aurora
New Orleans East
North Claiborne
Oak Park
Octavia Street
Old Spanish Trail
Pilotland
Pines Village
Pittari St.
Plum Orchard / West Lake Forest
Pontchartrain Park
Pontilly
Read Blvd
Resilience
S Galvez
Safe Routes to School
Saratoga Square
St Claude
St Louis Canal
St. Ann
St. Bernard
St. Charles
St. Roch
Streetscape
SWB
Taft Place
Traffic Advisory
Treme-Lafitte
Viavant-Lake Catherine
Village de L’Est
West Bank
West End
Wisner Bridge
Wright Rd
Youth Study Streets


Looking for work?

The City of New Orleans and the Sewerage & Water Board are hiring.

Find jobs with the City

Find jobs with S&WB

Connect to First Source


Contact us

You can contact us directly at roadwork@nola.gov
or by phone at (504) 658-ROAD (7623).